| Gewerk |
Kalenderwoche 2006 |
|
KW |
Datum Kalenderwoche |
| |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
|
|
|
|
|
| Ersttermin
mit Bauleiter |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
30.01.2006 |
- |
05.02.2006 |
| Baugrube/Sandplatte |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6 |
06.02.2006 |
- |
12.02.2006 |
| Abnahme
Baugrube/Sandplatte |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
13.02.2006 |
- |
19.02.2006 |
| Fundamentplatte |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
20.02.2006 |
- |
26.02.2006 |
| EG-Mauerwerk/Decke |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9 |
27.02.2006 |
- |
05.03.2006 |
| Gerüstbauarbeiten |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
06.03.2006 |
- |
12.03.2006 |
| Mgiebel/Richtfertig |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11 |
13.03.2006 |
- |
19.03.2006 |
| Richten |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
20.03.2006 |
- |
26.03.2006 |
| DG-I-Mauerwerk/Giebel |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13 |
27.03.2006 |
- |
02.04.2006 |
| Dacheindeckung |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14 |
03.04.2006 |
- |
09.04.2006 |
| Abnahme
Rohbau |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
10.04.2006 |
- |
16.04.2006 |
| Haustür- u.
Fenstermontage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
17.04.2006 |
- |
23.04.2006 |
| Rolladen |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17 |
24.04.2006 |
- |
30.04.2006 |
| Gipskarton/Dämmung |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18 |
01.05.2006 |
- |
07.05.2006 |
| Elektro-Installation
(Rohbau) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19 |
08.05.2006 |
- |
14.05.2006 |
| Innenputz |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
15.05.2006 |
- |
21.05.2006 |
| Außenputzdämmung |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21 |
22.05.2006 |
- |
28.05.2006 |
| Heizung/Sanitär
(Rohbau) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22 |
29.05.2006 |
- |
04.06.2006 |
| Dachkasten/Profilholz |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23 |
05.06.2006 |
- |
11.06.2006 |
| Estrich |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24 |
12.06.2006 |
- |
18.06.2006 |
| Außenputzdekor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
25 |
19.06.2006 |
- |
25.06.2006 |
| Abseite/Bodentr./Luk |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
26 |
26.06.2006 |
- |
02.07.2006 |
| Nacharbeiten |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
27 |
03.07.2006 |
- |
09.07.2006 |
| Elektro-Installation
(Endarbeiten) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
28 |
10.07.2006 |
- |
16.07.2006 |
| Heizung/Sanitär
(Mitte) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
29 |
17.07.2006 |
- |
23.07.2006 |
| Fliesenarbeiten |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30 |
24.07.2006 |
- |
30.07.2006 |
| Heizung/Sanitär
(End) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
31 |
31.07.2006 |
- |
06.08.2006 |
| Holztreppe |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
32 |
07.08.2006 |
- |
13.08.2006 |
| Innentürmontage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
33 |
14.08.2006 |
- |
20.08.2006 |
| Elast.
Verfugung Innen/Außen |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
34 |
21.08.2006 |
- |
27.08.2006 |
| Hausübergabe |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
35 |
28.08.2006 |
- |
03.09.2006 |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Legende: |
|
= |
Planung |
|
|
= |
Ausführung |
|
|
= |
Neue Planung nach
Winterverzögerung |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|